MONTHLY UPDATE


Brick, glass, and railing installations are nearing completion, and streetscaping work to begin end of january.
Landscape work at amenity area and courtyard nearing completion. window installation complete. lido panels and stucco in progress
Elevator has been installed. landscape within amenity area is inprogress. window installation is nearly complete
Commencement of interior suite finishes & exterior (amenity & courtyard) landscape work. preparations underway for crane removal mid aug
Interior suite framing, boarding and taping progressing. exterior finishing nearing completion at condominium, window & brick installation in progress at townhomes
Windows installed up to the 9th floor. preparing to pour roof slab of townhomes. lido panel installation is now complete
Windows installed up to 7th floor. brickwork is in progress and 2nd floor slab of townhomes are now being poured
Concrete pour at the roof slab underway. windows have been installed up to the 6th floor. work on townhomes to begin shortly
The 6th and 7th floor concrete pours are completed. 8th floor slab concrete pouring is ongoing. vertical pouring to 9th floor to begin mid january. window installation has begun
Concrete pouring for 5th floor slab and 5th floor vertical walls has been completed. 6th floor slab and vertical walls concrete pouring is on going
Concrete for 4th floor slab & 5th floor vertical walls is currently being poured. 5th floor slab concrete pouring will commence early november
Ground floor slab is nearing completion. forming & decking work is underway on the second floor slab.
Slab on grade is now complete. ground floor slab concrete pouring & forming is ongoing
Footings & foundation wall pours are now completed. slab on grade is near completion. forming work for ground floor is in progress
Backfilling along memory lane is ongoing. footings are now 95 percent complete. 5 of 8 foundation walls have been poured & the slab on grade is 60 percent complete. forming work for floors 1-3 is now in progress
Construction at the george is well underway. shoring & excavation has been completed. southern portion of the site along memory lane is being backfilled. footings are near completion & foundation walls are progressing

THE NEST ON ST. CLAIR WEST

Ridgewood I & II

Lemonwood Townhomes

Montgomery Square

Twenty-One Clairtrell